This overview brings together public operator data for points assigned to śląskie voivodeship using substations in OpenStreetMap or a manually verified assignment. Use it as a starting point and check the relevant operator’s current publication.
Generation-source data compiled for these operators: PSE, TAURON Dystrybucja. Voivodeship statistics include only points whose location is confirmed in OpenStreetMap or assigned manually. Substations marked as approximate (loc=geo) are excluded. Values are shown without conversion between operators.
| Substation / group (GPZ) | Operator | Voltage | Available capacity |
|---|---|---|---|
| Grupa Łazy | TAURON Dystrybucja | 110 kV | 15.0 MW |
| Grupa Łośnice | TAURON Dystrybucja | 110 kV | 15.0 MW |
| Grupa Żywiec | TAURON Dystrybucja | 110 kV | 15.0 MW |
| Grupa Pszczyna | TAURON Dystrybucja | 110 kV | 10.0 MW |
| Grupa Kopanina 2 | TAURON Dystrybucja | 110 kV | 5.0 MW |
| Grupa Moszczenica | TAURON Dystrybucja | 110 kV | 5.0 MW |
| Grupa Skoczów | TAURON Dystrybucja | 110 kV | 5.0 MW |
| Grupa Studzienna | TAURON Dystrybucja | 110 kV | 5.0 MW |
Do you have a solar PV, wind or energy-storage project in this region? Compare the data with the project documentation and the relevant operator’s current publication. Estimate grid connection fees with the Calculate connection fees tool.
Source: the network-operator publications listed above, aggregated in the CHECK CAPACITY tool. The figures cover points marked as generation sources that also meet this dataset’s location criteria. The data is for information only and does not constitute an offer or grid connection terms.