Calculate upfront costs before applying

Answer a few questions about the project to see upfront costs: a PLN 60/kW advance payment, a PLN 1/kW application fee and PLN 30–60/kW security. Statutory rates and deadlines for connections to grids above 1 kV (medium/high voltage).

Calculate cash requirementsAdvance payment and security calculated for your capacity.
Check the deadlinesStatutory deadlines, including 14 days to provide security after concluding the connection agreement.
Prepare your argumentsFor discussions with the grid operator and investor. The operator issues binding conditions.
Freeillustrative connection passport calculator
Full accessPassport calculated for your project capacity, with substation and queue dataPLN 19 excluding VAT/month for 3 monthsGet started what is included
Questions Passport Location Primary substation profile

Answer a few questions about the project and the Navigator compiles a Connection passport: fees, security and deadlines for your scenario. At the end, check the parcel location and the nearest primary substation profile.

Connection agreement expiry clock

From 30.04.2026 a connection agreement for a grid above 1 kV expires by operation of law where the connecting party fails to notify the operator in time that it has obtained a final building permit decision (Article 7(2a) of the Energy Law, added by the Act of 13.03.2026, Journal of Laws 2026 item 516). The deadline depends on the date the agreement was concluded and on the type of installation.

Agreements concluded on or after 30.04.2026
24 months from conclusion: photovoltaics with inverters and BESS storage (a permit for at least 80% of the capacity covered by the agreement) and consuming equipment (at least 50% of the capacity). 36 months: wind turbines, biogas and agricultural biogas installations, transformers and switchgear. 60 months: installations and facilities supplying railway traction networks.
Agreements concluded between 30.04.2022 and 29.04.2026
Deadlines counted from 30.04.2026: 30 months (photovoltaics, BESS, consuming equipment), 42 months (wind, biogas, transformers and switchgear), 60 months (railway supply). Basis: Article 13 of the amending act, applicable from 16.10.2026.
Agreements concluded before 30.04.2022
From 30.04.2026: 6 months for wind turbines, 3 months for the remaining installations (Article 14 of the amending act, applicable from 16.10.2026). The rule does not cover agreements under which part of the installation has already been connected, nor railway supply.
Extension of the deadline
On an application filed before the deadline expires, the operator extends it by no more than 24 months, once only, after an additional security of PLN 60 for each kilowatt of connection capacity, up to PLN 12,000,000, has been lodged (paragraphs 2h and 2i). Circumstances beyond the party’s control (natural disaster, acts of war, embargo, a Ministry of National Defence protection zone, supply chain disruption, protracted proceedings) protect against expiry once a statement with supporting documents has been filed (paragraphs 2b and 2c).
Exclusions
Nuclear investments and offshore wind farms carried out under special acts (paragraph 2j).

Enter the date the agreement was concluded to see the deadline.

We count deadlines under Article 112 of the Civil Code: a deadline in months ends at the close of the day whose date corresponds to the starting day, and where the last month has no such day, on the last day of that month. Legal status as at 15.09.2026.

This is a statutory deadline. The connection agreement itself may contain its own provisions on deadlines and on the consequences of missing them, so check the date of conclusion and the wording of the agreement in the document, and for an agreement predating 30.04.2026 also whether part of the installation has already been connected.

What Full access changes

The same connection passport. A different level of precision.

Without Full access

Select a capacity range and see amounts calculated for its lower and upper bounds.

Then calculate the amount for your project’s exact capacity yourself.

With Full access

Receive a passport calculated for your project’s exact capacity.

The result includes substation and queue data for the selected location.

Full accessPassport calculated for your location and capacity
included in the subscription
Connection passport · calculated for your location
Advance payment60 PLN/kWcalculated for your capacity
Security30–60 PLN/kWplus the connection conditions application fee and maximum advance payment
Statutory deadlineProvide security within 14 days of concluding the connection agreement, failing which the agreement expires (Article 7(8c9) of the Polish Energy Law).
The full version of this view with Full access: PLN 19 net/month for the first 3 months (PLN 23.37 including VAT), then PLN 199 excluding VAT/month (PLN 244.77 including VAT).
Renews automatically each month; cancel at any time. Your project and land listings are included at the same price, with no limit on the number of listings.
Start for PLN 19 excluding VAT/month See both options, including listing unlocks →
Illustrative connection passport calculator remains free.
Fixed price, no negotiation.
Legal information and limitations

Navigator results are for information only and do not constitute legal advice (Article 4(1) of the Polish Act on Legal Advisers and Article 4(1) of the Law on the Bar remain unaffected: advice on an individual matter is provided under a separate agreement). The rates shown here (PLN 60/kW advance payment, PLN 1/kW application fee and PLN 30–60/kW security) derive from Article 7(8a–8b1) of the Energy Law as amended by the Act of 13 March 2026 (Journal of Laws 2026, item 516), effective from 30 April 2026. Content is based on that Act. Exclusions: individual interpretation, URE/DSO decisions and the facts of a specific case. Legal position as at 11 June 2026.