Check available capacity

More filters
This filter works with Full access.
Substations within a radius of the address

We convert the address you enter into a point on the map. We send only the address text, without your IP address or account data.

Substations from operator lists

565

Loading substations…

What is free and what is paid

Free: what is where, meaning names, localities, technologies and entry dates. Paid: what follows for one site, one company and one unit, meaning the check result, capacities, totals and deadlines.

Free: map of six grid operators' substations with voltage and list dates, no account required
In Full access: capacity and connection queue at every substation, operators’ forecasts, matching the nearest entry in the operator’s capacity list to your plot, the grid at its location and the result of each layer on the plot card

Filtering and sorting by capacity are available in Full access. The free account provides the total available capacity by operator and voivodeship available capacity report. The dots “•••” indicate the value in Full access.

Do you have the location and substation from the list? Before applying, ask HWW about the grid connection.

  1. Available capacity according to the list
  2. Application queue in the vicinity
  3. Connection agreement and connection date
Ask HWW about grid connection

Summaries

Connection queue

1,836 entries in the application lists

Loading application lists…

Connection refusals

2025 report of the President of UREdomestic data, no list for the substation

Loading URE data…

Distribution system operators (DSO and OSDn)

register of the President of URE

Loading the operator list…

Pressure around the substation (WNS)

capacity of connection applications in the vicinity of the substation compared to available capacity from the operator's list

Loading substations…

Available capacity and queue in saved summaries

National totals over time

Loading summaries…

Report: available grid connection capacities

operator lists, queue and refusals in a single overview

Renewable generation curtailment

PSE data on solar and wind curtailments

Check a site

available capacity according to the operator's list, application queue, nature protection, local spatial development plan and flood risk for the specified location

Saved substations

substations marked with an asterisk

Available capacity by voivodeship

mazowieckieśląskiedolnośląskie

Available connection capacity by operator

PGE Dystrybucja

PGE Dystrybucja publishes available connection capacity for generation sources at 110 kV substations, together with a forecast for the coming years. Substations from its list appear on the map in the lubelskie, łódzkie, mazowieckie, podkarpackie, podlaskie, świętokrzyskie and warmińsko-mazurskie voivodeships.

Show on the map

TAURON Dystrybucja

TAURON Dystrybucja publishes available connection capacity for generation sources at 110 kV substations in the dolnośląskie, małopolskie, opolskie, podkarpackie and śląskie voivodeships. In its list of applications the operator also gives the connection group and divides applications into those under review and those planned for connection.

Show on the map

Enea Operator

Enea Operator publishes available connection capacity for generation sources by GPZ substation and a separate list for consumers by county. Substations from its list appear on the map in the dolnośląskie, kujawsko-pomorskie, lubuskie, pomorskie, wielkopolskie and zachodniopomorskie voivodeships; switch to the consumer list with the “Capacity for” field in the filters.

Show on the map

Energa-Operator

Energa-Operator publishes available connection capacity at 110 kV substations in separate lists for generation sources and for consumers. Substations from its list appear on the map in the kujawsko-pomorskie, łódzkie, mazowieckie, pomorskie, warmińsko-mazurskie, wielkopolskie and zachodniopomorskie voivodeships; switch to the consumer list with the “Capacity for” field in the filters.

Show on the map

Stoen Operator

Stoen Operator publishes available connection capacity for generation sources in its 110 kV network in Warsaw.

Show on the map
How to search and where connection deadlines come from
  • Enter the name of a substation or a listing row, an operator or a voivodeship. The search also covers the composition of group rows, so a substation name from a “Group …” row matches that row.
  • Substations within a radius of the address measure the straight-line distance from the specified point to the entry in the operator's capacity list.
  • The deadlines in the connection box come from Article 7(2a) of the Energy Law (PE):
    • Regional pages include points with a location confirmed in OpenStreetMap or manually assigned. Points with an approximate location are excluded from voivodeship statistics.
    Scope of the queue and caveats

    Connection queue: entities applying to connect generators above 1 kV, from grid operators' publications.

    The RES curtailment line above the table gives PSE's national data (the whole national power system, a grid saturation indicator), not values for a single substation; peak instantaneous capacity, energy not taken and wind curtailment are on the RES curtailment page.

    At PGE Dystrybucja, Enea, Energa, Stoen and PSE, the layer counts applications submitted, connection conditions issued, agreements concluded and refusals, for generators only, while at TAURON Dystrybucja all list items according to the previous scope are included; the queue total comprises applications submitted, connection conditions issued and agreements concluded, while refusals are shown separately, outside the total.

    Split into Group II/III and stages in progress and planned is provided only by TAURON Dystrybucja. Generator capacity is the capacity injected into the grid from the operator’s publication: 1223 rows of generators with installed capacity 5657,3 MW without injected capacity are not included in the sums. In the full dataset, the unit is a GPZ substation when the publication provides it, while in other rows the name comes from the location description, so some entries do not have a map marker, although they are included in the sums. Without full access, you can see the sums for the entire dataset and three types of rows: TAURON Dystrybucja counties (the previous list format), towns from the operator's towns column with at least 3 applications included in the sum, and aggregate rows without location. Rows for substations, switchgear, and lines, names from the location description, and towns with 1 or 2 applications are available with full access. The overview layer reflects the status as of the operators' publication dates; binding data is confirmed by the relevant DSO/TSO.

    Connection refusals: data scope

    The scope of data on refusals is loaded from a data file.

    Operator categories in the URE register

    Full list of system operators from the URE open register: OSDp (5 large OSDs connected to the transmission grid), OSDn (local/industrial operators), ZSD (closed distribution systems), OSPe (transmission system operator = PSE). Each operator publishes available capacity on its website.

    How we calculate pressure around the substation

    The indicator is the sum of application capacities within a 20 km radius divided by the total of that capacity and the capacity from the operator's list. It also includes applications from other operators and other connection points. It does not measure physical grid saturation or connection availability, nor is it a station capacity reserve. The list takes stations from the current selection in the list above.

    How to read saved summaries

    Aggregates from saved summaries. Dates indicate the summary recording, and operator publications have different dates and ranges. Changes in the total may also result from data updates or corrections; they do not solely indicate changes in grid availability.